Incapital Holdings, LLC – Boca Raton, Florida

Incapital Holdings, LLC

PROJECT OVERVIEW:

Because the base building was unavailable for the commencement of construction until six weeks prior to the required occupancy date, the specter of achieving custom millwork and glazing was hanging over everyone’s head. In order to accomplish the goal the Owner “teamed” the Architect and the General Contractor from start of design. Long lead items were identified and ordered during design, a pre-fabricated wall and glazing system from DIRTT systems was employed into the design solution and early demolition and framing was negotiated with the City of Boca Raton. During design major subcontractors, i.e., mechanical, plumbing, electrical, low voltage, IT and millwork were paired with the design team to create realistic solutions with minimal conflicts.

FEATURES:

Glazing system from DIRTT systems
Pre-fabricated wall

SQUARE FEET:

13,000